PEPPOL-T76-R004
If both delivery period start date and delivery period end date are given then the end date SHALL be later or equal to the start date.
error: the document is invalid
What the rule checks
As the rule set's publisher wrote it. The rule runs on every element the context matches, and fails where the test is false; the validator reports the line of that element.
Context
cac:PromisedDeliveryPeriod | cac:OrderLine/cac:LineItem/cac:PromisedDeliveryPeriod
Test
(exists(cbc:EndDate) and exists(cbc:StartDate) and (cbc:EndDate) >= (cbc:StartDate)) or not(exists(cbc:StartDate)) or not(exists(cbc:EndDate))
Checked with Peppol Order Response